[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102396":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102396,779,2,"多选题","下列属于招标采购阶段合同管理任务的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","开展建设工程项目招标采购的总体策划",true,{"key":16,"text":17,"correct":14},"B","根据标准文本编制招标文件和合同条件",{"key":19,"text":20,"correct":21},"C","制定完善的合同管理制度和实施计划",false,{"key":23,"text":24,"correct":14},"D","细化项目参建各相关方的合同界面管理",{"key":26,"text":27,"correct":14},"E","合理选择适合建设工程特点的合同计价方式","ABDE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]