[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102388":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102388,779,2,"多选题","关于单价合同的说法，正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","投标报价单中总价和单价计算结果不一致时，以单价为准调整总价",true,{"key":16,"text":17,"correct":14},"B","对于投标书中出现明显的数字计算错误，业主有权利先作修改再评",{"key":19,"text":20,"correct":14},"C","采用单价合同时，业主和承包人都不担心存在工程量方面的风险",{"key":22,"text":23,"correct":14},"D","采用变动单价合同时，承包人的风险相对较小",{"key":25,"text":26,"correct":27},"E","采用固定单价合同时，业主招标准备时间较长",false,"ABCD","单价合同又可分为固定单价合同和可变单价合同两种形式。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]