[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102380":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102380,779,2,"多选题","FIDIC系列合同，《施工合同条件》中关于修补工作说法正确的是（）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","将不符合合同规定的永久设备或材料从现场移走并进行更换",true,{"key":16,"text":17,"correct":14},"B","对不符合合同规定的任何工作进行返工",{"key":19,"text":20,"correct":14},"C","实施任何因事故导致的为保护工程安全而急需的工作",{"key":22,"text":23,"correct":14},"D","实施任何因不可预见事件等导致的为保护工程安全而急需的工作",{"key":25,"text":26,"correct":27},"E","如果是业主方原因等导致的，承包商无权提出索赔。",false,"ABCD","2020版教材P153-157 修补工作 尽管先前已经通过了试验或颁发了证书，工程师仍可以指示承包商: (1)将不符合合同规定的永久设备或材料从现场移走并进行更换; (2) 对不符合合同规定的任何工作进行返工; (3) 实施任何因事故、不可预见事件等导致的为保护工程安全而急需的工作。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]