[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102378":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102378,779,2,"多选题","根据银皮书，承包商有权提出要求延长竣工时间的索赔的情形有（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","异常不利的气候条件",false,{"key":16,"text":17,"correct":18},"B","根据合同变更的规定调整竣工时间",true,{"key":20,"text":21,"correct":18},"C","根据合同条件承包商有权获得工期顺延",{"key":23,"text":24,"correct":18},"D","由业主或在现场的业主的其他承包商造成的延误或阻碍",{"key":26,"text":27,"correct":14},"E","由于流行病或政府行为导致的不可预见的人员或货物的短缺","BCD","2020版教材P158-161 根据银皮书，承包商有权提出要求延长竣工时间的索赔的情形只有下列3 种: (1)根据合同变更的规定调整竣工时间; (2)根据合同条件承包商有权获得工期顺延; (3)由业主或在现场的业主的其他承包商造成的延误或阻碍。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]