[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102375":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102375,779,2,"多选题","《设计采购施工（EP C）\u002F交钥匙合同条件》中，承包商的主要责任和义务包括（）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发出变更通知",false,{"key":16,"text":17,"correct":18},"B","办理工程保险",true,{"key":20,"text":21,"correct":18},"C","负责承包商设备",{"key":23,"text":24,"correct":18},"D","负责现场保安",{"key":26,"text":27,"correct":18},"E","对业主人员进行工程操作和维修培训","BCDE","2020版教材P157-158 A选项为业主的主要责任和义务，B、C、D、E为承包商的主要责任和义务。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]