[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102373":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102373,779,2,"多选题","关于风险CM模式的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","CM合同属于管理承包合同",true,{"key":16,"text":17,"correct":14},"B","CM合同采用成本加酬金的计价方式",{"key":19,"text":20,"correct":14},"C","CM承包商不赚取总包、分包合同的差价",{"key":22,"text":23,"correct":24},"D","CM承包商属于专业咨询机构",false,{"key":26,"text":27,"correct":24},"E","CM承包商在工程设计阶段参与合同管理","ABC","本题考查的是CM合同模式。选项D，CM合同类型属于管理承包合同，有别于施工总承包商承包后对分包合同的管理。与雇主签订合同的承包商，属于承担施工的承包商公司，而非建筑师或专业咨询机构；选项E，工作内容包括施工前阶段的咨询服务和施工阶段的组织、管理工作",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]