[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102361":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102361,779,2,"多选题","在FIDIC设计采购施工EPC合同条件中，业主应对 资料中（ ）的正确性负责。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不可预见的困难情况",false,{"key":16,"text":17,"correct":14},"B","施工进度计划",{"key":19,"text":20,"correct":21},"C","对工程的预期目标的说明",true,{"key":23,"text":24,"correct":14},"D","放线数据",{"key":26,"text":27,"correct":21},"E","工程竣工的试验和性能的标准","CE","本题考查的是《设计采购施工（EPC）\u002F交钥匙合同条件》典型条款分析。选项A，为承包商承担责任的事项。选项B，由承包商编制。选项D，放线数据需要承包商核实，不完全依靠甲方的数据。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]