[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102345":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102345,779,2,"多选题","关于工程款支付管理说法错误的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同价格包括签约合同价以及按照合同约定进行的调整",false,{"key":16,"text":17,"correct":18},"B","设计施工总承包合同对预付款的规定与标准施工合同不同",true,{"key":20,"text":21,"correct":18},"C","除专用条款另有约定外，工程进度付款按季支付",{"key":23,"text":24,"correct":14},"D","合同价格包括承包人依据法律规定或合同约定应支付的规费和税金",{"key":26,"text":27,"correct":14},"E","价格清单列出的任何数量仅为估算的工程量","BC","2020版教材P129-131 本题考查的是工程款支付管理。选项B错误，设计施工总承包合同对预付款的规定与标准施工合同相同；选项C错误，除专用条款另有约定外，工程进度付款按月支付。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]