[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102344":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102344,779,2,"多选题","某采用标准设计施工总承包合同的工程项目，合同履行出现合同进度计划工作的延误，应由发包人承担延长工期和增加费用并支付合理利润的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","发包人要求的设计变更",true,{"key":16,"text":17,"correct":14},"B","发包人未按期审查承包人文件",{"key":19,"text":20,"correct":21},"C","承包人未按已确认修改的设计文件实施",false,{"key":23,"text":24,"correct":14},"D","发包人提供的材料延误",{"key":26,"text":27,"correct":21},"E","异常不利的气候条件","ABD","2020版教材P128-129 2020版教材P122。在履行合同过程中非承包人原因导致合同进度计划工作延误，应给承包人延长工期和（或）增加费用，并支付合理利润。选项E是一个特例，虽然也是非承包人原因，但只可以延长工期和增加费用，不能补偿合理利润。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]