[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102338":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102338,779,2,"多选题","在设计施工总承包合同中，关于发包人要求中的错误，以下说法不正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人对错误的修改，按变更对待",false,{"key":16,"text":17,"correct":18},"B","承包人复核时未发现发包人要求的错误，发包人必须承担实施过程中的损失",true,{"key":20,"text":21,"correct":18},"C","对工程的工艺安排或要求的错误，发包人不需承担责任",{"key":23,"text":24,"correct":14},"D","承包人复核发包人要求，发现错误的，及时书面通知发包人",{"key":26,"text":27,"correct":14},"E","对工程或其任何部分的功能要求的错误，发包人要承担责任","BC","2020版教材P123-126 本题考查的是订立合同时需要明确的内容。选项B，承包人复核时发现发包人要求的错误时，分无条件补偿条款和有条件补偿条款，承包人复核时未发现发包人要求中存在错误的，承包人自行承担由此导致增加的费用和(或)工期延误。选项D，对工程的工艺安排或要求错误，无论承包人复核时发现与否，导致承包人增加费用和(或)延误的工期，均由发包人承担，并向承包人支付合理利润 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]