[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102333":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102333,779,2,"多选题","根据《标准设计施工总承包合同》，无论承包人复核是否发现问题，导致承包人费用增加时，均由发包人承担责任的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","引用的原始数据和资料错误",true,{"key":16,"text":17,"correct":14},"B","对工程的功能要求错误",{"key":19,"text":20,"correct":21},"C","对工程进度的要求不合理",false,{"key":23,"text":24,"correct":14},"D","试验和检验标准不准确",{"key":26,"text":27,"correct":14},"E","对项目生产工艺的要求错误","ABDE","2020版教材P123-126 本题考查的是订立合同时需要明确的内容。无论承包人复核时发现与否，由于以下资料的错误，导致承包人增加费用和(或)延误的工期，均由发包人承担，并向承包人支付合理利润：(1)发包人要求中引用的原始数据和资料；(2)对工程或其任何部分的功能要求；(3)对工程的工艺安排或要求；(4)试验和检验标准；(5)除合同另有约定外，承包人无法核实的数据和资料 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]