[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102331":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102331,779,2,"多选题","不可预见物质条件涉及的范围与标准施工合同相同，但通用条款中对风险责任承担的规定条款有（），双方应当明确本合同选用哪一条款的规定。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","风险由承包人承担",true,{"key":16,"text":17,"correct":18},"B","风险由工程师承担",false,{"key":20,"text":21,"correct":14},"C","风险由发包人承担",{"key":23,"text":24,"correct":18},"D","风险由监理人承担",{"key":26,"text":27,"correct":18},"E","风险由分包人承担","AC","2020版教材P123-126 不可预见物质条件涉及的范围与标准施工合同相同，但通用条款中对风险责任承担的规定有两个供选择的条款：一是此风险由承包人承担；二是由发包人承担。因此，本题的正确答案为AC。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]