[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102329":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102329,779,2,"多选题","设计施工总承包合同规定，发包人要求文件说明的其他要求包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对承包人的主要人员资格要求",true,{"key":16,"text":17,"correct":18},"B","承包、设备供应商",false,{"key":20,"text":21,"correct":14},"C","相关审批、核准和备案手续的办理",{"key":23,"text":24,"correct":14},"D","对项目业主人员的操作培训",{"key":26,"text":27,"correct":14},"E","缺陷责任期的服务要求","ACDE","2020版教材P121-123 设计施工总承包合同规定，发包人要求文件应说明11个方面的内容，其中其他要求包括：对承包人的主要人员资格要求；相关审批、核准和备案手续的办理；对项目业主人员的操作培训；分包；设备供应商；缺陷责任期的服务要求等。因此，本题的正确答案为CDE。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]