[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102327":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102327,779,2,"多选题","下列关于设计施工总承包合同模式下分包工程的说法错误的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人不得将承包的全部工程转包给第三人",false,{"key":16,"text":17,"correct":18},"B","分包工作可以自行分包",true,{"key":20,"text":21,"correct":14},"C","要求分包人是具有实施工程设计和施工能力的合格主体",{"key":23,"text":24,"correct":18},"D","分包人的资质能力不需要经过监理人审查",{"key":26,"text":27,"correct":14},"E","分包人的资格能力应与其分包工作的标准和规模相适应","BD","2020版教材P121 本题考查的是设计施工总承包合同模式下对分包工程的规定。分包工作需要征得发包人同意。发包人已同意投标文件中说明的分包，合同履行过程中承包人还需要分包的工作，仍应征得发包人同意。分包人的资格能力应与其分包工作的标准和规模相适应，其资质能力的材料应经监理人审查。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]