[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102325":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102325,779,2,"多选题","下列关于设计施工总承包合同模式下分包工程的说法，错误的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包人不得将其承包的全部工程肢解后以分包的名义分别转包给第三人",false,{"key":16,"text":17,"correct":18},"B","发包人已同意投标文件中说明的分包，分包工作不需要经发包人同意",true,{"key":20,"text":21,"correct":14},"C","承包人不得将设计和施工的主体、关键性工作的施工分包给第三人",{"key":23,"text":24,"correct":18},"D","分包人的资质能力不需要进过监理人审查",{"key":26,"text":27,"correct":14},"E","发包人同意分包的工作，承包人应向发包人和监理人提交分包合同副本","BD","2020版教材P121 本题考查的是设计施工总承包合同模式下对分包工程的规定。发包人已同意投标文件中说明的分包，分包工作仍应经发包人同意。分包人的资格能力应与其分包工作的标准和规模相适应，其资质能力的材料应经监理人审查。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]