[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102320":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102320,779,2,"多选题","根据《标准设计施工总承包合同》，关于竣工后试验的说法，错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发包人在场的情况下承包人进行竣工后试验",false,{"key":16,"text":17,"correct":18},"B","竣工后试验由监理人组织发包人和承包人进行",true,{"key":20,"text":21,"correct":14},"C","发包人应将竣工后试验的日期提前21天通知承包人",{"key":23,"text":24,"correct":18},"D","监理人在竣工后试验合格时向承包人签发工程接收证书",{"key":26,"text":27,"correct":14},"E","竣工后试验通常在缺陷责任期内工程稳定运行一段时间后进行","BD","2020版教材P136-137 竣工后试验按专用条款的约定由发包人或承包人进行，故选项B错误。经验收合格工程，监理人经发包人同意后向承包人签发工程接收证书，故选项D错误。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]