[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102311":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102311,779,2,"多选题","在设计施工阶段的总承包合同中，关于竣工验收管理说法，错误的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","承包人应提前28天将申请竣工试验的通知送达监理人",true,{"key":16,"text":17,"correct":14},"B","承包人完成工程竣工应满足的条件后，即可向监理人报送竣工验收申请报告",{"key":19,"text":20,"correct":21},"C","经验收合格的工程，以提交竣工验收申请报告的日期为准",false,{"key":23,"text":24,"correct":21},"D","设计施工总承包合同通用条款对竣工结算的规定与标准施工合同相同",{"key":26,"text":27,"correct":14},"E","经验收合格工程，监理人可随时向承包人签发工程接收证书","ABE","2020版教材P136-137 本题考查的是竣工验收管理。选项A，承包人应提前21天将申请竣工试验的通知送达监理人。选项B，承包人完成工程竣工应满足的条件后，并提交了竣工文件、竣工图、最终操作和维修手册后，即可向监理人报送竣工验收申请报告。选项E，经验收合格工程，监理人经发包人同意后向承包人签发工程接收证书 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]