[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102310":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102310,779,2,"多选题","承包人应提前21天将申请竣工试验的通知送达监理人，并按照专用条款约定的份数，向监理人提交()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","竣工验收报告",false,{"key":16,"text":17,"correct":18},"B","竣工记录",true,{"key":20,"text":21,"correct":14},"C","签证文件",{"key":23,"text":24,"correct":18},"D","暂行操作",{"key":26,"text":27,"correct":18},"E","维修手册","BDE","2020版教材P136-137 本题考查的是竣工验收管理。承包人应提前21天将申请竣工试验的通知送达监理人，并按照专用条款约定的份数，向监理人提交竣工记录、暂行操作和维修手册 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]