[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102309":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102309,779,2,"多选题","关于承包人编制的进度付款支付分解表，说法正确的有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","勘察设计费按照提供提交勘察设计阶段性成果文件的时间、对应的工作量进行分解",true,{"key":16,"text":17,"correct":14},"B","材料和工程设备费分别按订立采购合同、进场验收合格、安装就位、工程竣工等阶段和专用条款约定的比例进行分解",{"key":19,"text":20,"correct":14},"C","技术服务培训费按照价格清单中的单价，结合合同进度计划对应的工作量进行分解",{"key":22,"text":23,"correct":24},"D","其他工程价款按照价格清单中的价格，结合合同进度计划对应的工作量进行分解",false,{"key":26,"text":27,"correct":24},"E","其他工程价款按照已标价工程量清单中的价格，结合合同进度计划对应的工程量或者比例进行分解","ABC","2020版教材P129-131 本题考查的是工程款支付管理。选项DE，其他工程价款，按照价格清单中的价格，结合合同进度计划拟完成的工程量或者比例进行分解 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]