[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102308":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102308,779,2,"多选题","在设计施工阶段的总承包合同中，关于工程款支付管理说法，错误的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","合同价格就是签约合同价",true,{"key":16,"text":17,"correct":18},"B","设计施工总承包合同对预付款的规定与标准施工合同相同",false,{"key":20,"text":21,"correct":14},"C","除专用条款另有约定外，工程进度付款按季支付",{"key":23,"text":24,"correct":18},"D","合同价格包括承包人依据法律规定或合同约定应支付的规费和税金",{"key":26,"text":27,"correct":14},"E","价格清单列出的任何数量为承包人实施工程的实际工程量","ACE","2020版教材P129-131 本题考查的是工程款支付管理。选项A，合同价格包括签约合同价以及按照合同约定进行的调整。选项C，付款时间除专用条款另有约定外，工程进度付款按月支付。选项E，价格清单列出的任何数量仅为估算的工作量，不视为要求承包人实施工程的实际或准确工作量 。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]