[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102304":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102304,779,2,"多选题","根据标准设计施工总承包合同通用条款的规定，下列说法不正确的是（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","出入施工场地的道路通行权以及修建场外设施的权利应当由发包人负责办理并承担费用",true,{"key":16,"text":17,"correct":14},"B","计日工和暂估价应当包括在合同价格内，实施过程中不再另行考虑",{"key":19,"text":20,"correct":14},"C","不可预见物质条件属于应当由发包人承担的风险",{"key":22,"text":23,"correct":14},"D","施工设备或临时设施应当由承包人提供",{"key":25,"text":26,"correct":27},"E","采用无条件补偿条款时，发包人要求中的错误导致承包人的损失应当由发包人承担",false,"ABCD","标准设计施工总承包合同通用条款给出两种可选用的约定形式的事项",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]