[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102284":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102284,779,2,"多选题","下列关于设计施工总承包合同的不足，说法正确的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","固定工期.固定费用",false,{"key":16,"text":17,"correct":14},"B","增加设计变更",{"key":19,"text":20,"correct":14},"C","增加承包人索赔",{"key":22,"text":23,"correct":24},"D","设计方案不一定最优",true,{"key":26,"text":27,"correct":24},"E","发包人对承包人的监督和检查力度减弱","DE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]