[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102283":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102283,779,2,"多选题","设计施工总承包方式的缺点包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工期与费用不固定",false,{"key":16,"text":17,"correct":18},"B","设计不一定是最优方案",true,{"key":20,"text":21,"correct":14},"C","建设工期延长",{"key":23,"text":24,"correct":14},"D","增加设计变更",{"key":26,"text":27,"correct":18},"E","减弱实施阶段发包人对承包人的监督和检查","BE","2020版教材P120 设计施工总承包方式的缺点包括：(1)设计不一定是最优方案；(2)减弱实施阶段发包人对承包人的监督和检查。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]