[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102253":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102253,779,2,"多选题","与施工和材料设备投标报价相比，虽然设计投标报价占项目总投资额的比例不大，但设计方案对工程项目往往更具（）影响。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","全局性",true,{"key":16,"text":17,"correct":14},"B","长效性",{"key":19,"text":20,"correct":14},"C","创新性",{"key":22,"text":23,"correct":24},"D","实用性",false,{"key":26,"text":27,"correct":24},"E","经济性","ABC","2020版教材P25-26 在招标标的物特征上，勘察设计是工程建设项目前期最为重要的工作内容，设计阶段是决定建设项目性能，优化和控制工程质量及工程造价最关键、最有利的阶段，设计成果将对工程建设和项目交付使用后的综合效益起重要作用。与施工和材料设备投标报价相比，虽然设计投标报价占项目总投资额的比例不大，但设计方案对工程项目往往更具全局性、长效性和创新性影响。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]