[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102241":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102241,779,2,"多选题","采用综合评估法对设计投标文件进行详细评审时的内容包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资信业绩评审",true,{"key":16,"text":17,"correct":18},"B","资格评审",false,{"key":20,"text":21,"correct":18},"C","响应性评审",{"key":23,"text":24,"correct":14},"D","设计方案评审",{"key":26,"text":27,"correct":14},"E","投标报价评审","ADE","3、评标分为初步评审和详细评审两个阶段",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]