[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102233":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102233,779,2,"多选题","在勘察设计评标中，以下（ ）属于详细评审的因素。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","响应性评审",false,{"key":16,"text":17,"correct":18},"B","资信业绩",true,{"key":20,"text":21,"correct":18},"C","勘察纲要或设计方案",{"key":23,"text":24,"correct":18},"D","投标报价",{"key":26,"text":27,"correct":14},"E","资格评审","BCD","本题考查的是勘察设计评标的程序。选AE属于初步评审的因素。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]