[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102225":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102225,779,2,"多选题","工程设计招标，可以包括以下（ ）的一个或多个阶段。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","方案设计",true,{"key":16,"text":17,"correct":14},"B","初步设计",{"key":19,"text":20,"correct":21},"C","可行性研究设计",false,{"key":23,"text":24,"correct":14},"D","施工图设计",{"key":26,"text":27,"correct":21},"E","竣工图设计","ABD","本题考查的是工程勘察设计招标主要工作内容。还包括扩大初步设计，但没有可行性研究设计及竣工图设计阶段。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]