[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102207":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102207,779,2,"多选题","编制勘察设计招标文件时，具体勘察和设计范围应当根据（）之间的关联内容进行确定，并在专用合同条款中约定。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程范围",true,{"key":16,"text":17,"correct":18},"B","投资范围",false,{"key":20,"text":21,"correct":14},"C","阶段范围",{"key":23,"text":24,"correct":18},"D","技术范围",{"key":26,"text":27,"correct":14},"E","工作范围","ACE","2、工程勘察设计范围要求 具体勘察和设计范围应当根据工程范围、阶段范围和工作范围三者之间的关联内容进行确定，并在专用合同条款中约定。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]