[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102202":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102202,779,2,"多选题","建设工程勘察设计发包的方式为（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","招标发包",true,{"key":16,"text":17,"correct":14},"B","直接发包",{"key":19,"text":20,"correct":21},"C","转包",false,{"key":23,"text":24,"correct":21},"D","工程采购",{"key":26,"text":27,"correct":21},"E","间接发包","AB","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]