[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102172":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102172,779,2,"多选题","最低评标价法采购材料和通用型设备时以投标价为基础，将评审各要素按预定方法换算成相应价格值，增加或减少到报价上形成评标价。投标价之外还需考虑的因素通常包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","运输费用",true,{"key":16,"text":17,"correct":18},"B","销售量",false,{"key":20,"text":21,"correct":14},"C","付款条件",{"key":23,"text":24,"correct":14},"D","设备性能、生产能力",{"key":26,"text":27,"correct":14},"E","零配件和售后服务","ACDE","2020版教材P68-70 最低评标价法采购材料和通用型设备时以投标价为基础，将评审各要素按预定方法换算成相应价格值，增加或减少到报价上形成评标价。在投标价之外还需考虑的因素通常包括运输费用、交货期、付款条件、零配件、售后服务、产品性能、生产能力等。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]