[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102140":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102140,779,2,"多选题","下列建设工程材料和设备的采购适宜直接向供货商订购的是（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","采购数额不大的建筑材料和标准规格产品",false,{"key":16,"text":17,"correct":14},"B","采购大宗及重要建筑材料和设备",{"key":19,"text":20,"correct":21},"C","零星采购",true,{"key":23,"text":24,"correct":21},"D","必须由原供货商提供产品",{"key":26,"text":27,"correct":21},"E","只能从一家供应厂商获得","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]