[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102135":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102135,779,2,"多选题","下列对各报价方式理解正确的是（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","EXW价不包含货物运至施工现场的运输费用和保险费",true,{"key":16,"text":17,"correct":14},"B","FCA价包含将货物交由承运人保管之前的一切运输费用",{"key":19,"text":20,"correct":14},"C","FOB价不包含从装运港运至目的港的运费",{"key":22,"text":23,"correct":24},"D","CIF价包含从装运港运至目的地的运费",false,{"key":26,"text":27,"correct":24},"E","CIP价不包含保险费","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]