[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102131":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102131,779,2,"多选题","施工现场交货价包括（ ）费用在内。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","出厂价",true,{"key":16,"text":17,"correct":18},"B","仓库交货价",false,{"key":20,"text":21,"correct":14},"C","运至施工现场的内陆运输费",{"key":23,"text":24,"correct":14},"D","保险费",{"key":26,"text":27,"correct":18},"E","施工现场保管费","ACD","本题考查的是材料设备采购招投标报价方式。施工现场交货价=出厂价+运至施工现场的内陆运输费+保险费。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]