[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102130":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102130,779,2,"多选题","对于既有设备采购又有安装服务的项目，以下说法正确的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","应当将设备和安装分开招标",false,{"key":16,"text":17,"correct":14},"B","应当将设备和安装合并招标",{"key":19,"text":20,"correct":21},"C","设备占费用比例大的，可按设备招标",true,{"key":23,"text":24,"correct":21},"D","安装工程占费用比例大的，可按安装工程招标",{"key":26,"text":27,"correct":14},"E","无论设备及安装工程占费用比例多大，均按设备招标","CD","本题考查的是材料设备采购招标特点。对于既有设备采购又有安装服务的项目，可以采用设备和安装分开招标，也可以合并招标。采用合并招标的，可以按照各部分所占的费用比例来确定具体招标类型。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]