[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102123":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102123,779,2,"多选题","（2020年真题）根据《标准施工招标文件》，施工评标中，对施工组织设计和项目管理机构的评审内容包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工方案的技术措施",true,{"key":16,"text":17,"correct":14},"B","质量、安全、环境保护管理体系与措施",{"key":19,"text":20,"correct":14},"C","工程进度计划、资源配置计划",{"key":22,"text":23,"correct":24},"D","技术负责人及主要管理人员配置",false,{"key":26,"text":27,"correct":24},"E","工程投资绩效评审方案","ABC","P54-57 施工组织设计和项目管理机构评审的因素一般包括施工方案与技术措施、质量管理体系与措施、安全管理体系与措施、环境保护管理体系与措施、工程进度计划与措施、资源配备计划、技术负责人、其他主要成员、施工设备、试验和检测仪器设备等。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]