[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102113":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102113,779,2,"多选题","(2017年真题)关于综合评估价法中，，初步评审的表述，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","初步评审分为形式评审、资格评审（适用于资格后审）和响应性评审三个方面，主要检查投标书是否满足招标文件的要求",true,{"key":16,"text":17,"correct":18},"B","审查内容和评审重点与经评审的最低投标价法完全不同",false,{"key":20,"text":21,"correct":14},"C","投标报价有算术错误的，评标委员会按相关原则对投标报价进行修正，修正的价格经投标人书面确认后具有约束力",{"key":23,"text":24,"correct":14},"D","投标报价有算术错误，但投标人不接受修正价格的，投标作废标处理",{"key":26,"text":27,"correct":18},"E","总价金额与依据单价计算出的结果不一致的，以总价金额为准","ACD","（一）初步评审 1.评审内容 ①形式评审标准；②资格评审标准（适用于资格后审）；③响应性评审标准；只要有一项不合格，作废标处理。审查内容和评审重点与最低投标价法相同。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]