[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102111":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102111,779,2,"多选题","(2016年真题)关于最低评标价法的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","该方法适用于具有通用技术，性能标准没有特殊要求的项目评标",true,{"key":16,"text":17,"correct":14},"B","该方法一般将投标人施工组织设计审查放在初步评审阶段",{"key":19,"text":20,"correct":21},"C","中标人应按中选的投标人的评标价与招标人签订合同",false,{"key":23,"text":24,"correct":21},"D","按评标价由高到低对投标人进行排序",{"key":26,"text":27,"correct":21},"E","投标人可以低于成本的价格报价","AB","本题考查的是经评审的最低投标价法。选项C，中标人应按投标报价与招标人签订合同；选项E，投标人不可以以低于成本的价格报价。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]