[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102107":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102107,779,2,"多选题","(2015年真题)在施工评标中，综合评估法中详细评审的因素包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资质条件",false,{"key":16,"text":17,"correct":18},"B","施工组织设计",true,{"key":20,"text":21,"correct":18},"C","项目管理机构",{"key":23,"text":24,"correct":18},"D","投标报价",{"key":26,"text":27,"correct":18},"E","其它评分因素","BCDE","本题考查的是综合评估法的评审因素。主要包括四项。选项A，资质条件在资格预审时考虑，不在评标中打分。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]