[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102106":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102106,779,2,"多选题","(2015年真题)建设工程施工招标初步评审过程中，应当否决投标的情形有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","投标文件中大写金额与小写金额不一致的",false,{"key":16,"text":17,"correct":14},"B","投标文件中总价金额与单价金额不一致的",{"key":19,"text":20,"correct":21},"C","投标人的商务条件超过招标人允许偏离的最大范围的",true,{"key":23,"text":24,"correct":21},"D","投标报价低于成本又无法提供说明和证据的",{"key":26,"text":27,"correct":21},"E","不按评标委员会要求澄清、说明或补正投标文件偏差的","CDE","本题考查的是可以否决投标的情况。选项AB，可以经评标委员会修正，投标人予以书面确认的情况。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]