[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102105":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102105,779,2,"多选题","(2015年真题)根据《标准施工招标文件》，应当进行重新招标的情形有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","投标截止时间后招标人不同意开标的",false,{"key":16,"text":17,"correct":18},"B","投标截止时间止，投标人少于3家的",true,{"key":20,"text":21,"correct":14},"C","投标人投诉中标人的",{"key":23,"text":24,"correct":18},"D","经评标委员会评审后否决所有投标的",{"key":26,"text":27,"correct":14},"E","招标人不接受评标评审结果的","BD","本题考查的是工程施工招标程序。有下列情形之一的，招标人在分析招标失败的原因并采取相应措施后，应当依法重新招标：（1）投标截止时间止，投标人少于3个的；（2）经评标委员会评审后否决所有投标的。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]