[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102085":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102085,779,2,"多选题","施工组织设计和项目管理机构评审的因素一般包括（ ）；资源配备计划；技术负责人；其他主要人员；施工设备；试验、检测仪器设备等。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工方案与技术措施",true,{"key":16,"text":17,"correct":18},"B","已标价工程量清单",false,{"key":20,"text":21,"correct":14},"C","环境保护管理体系与措施",{"key":23,"text":24,"correct":14},"D","质量管理体系与措施",{"key":26,"text":27,"correct":14},"E","工程进度计划与措施","ACDE","2020版教材P54-57 施工组织设计和项目管理机构评审的因素一般包括：施工方案与技术措施；质量管理体系与措施；安全管理体系与措施；环境保护管理体系与措施；工程进度计划与措施；资源配备计划；技术负责人；其他主要人员；施工设备；试验和检测仪器设备等。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]