[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102065":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102065,779,2,"多选题","根据《标准施工招标文件》，关于建设工程施工评标的说法，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","评标过程可分为初步评审和详细评审两个阶段",true,{"key":16,"text":17,"correct":14},"B","初步评审检查投标书是否对招标文件做出实质性响应",{"key":19,"text":20,"correct":21},"C","评标委员会不得主动提出对投标文件澄清或补正要求",false,{"key":23,"text":24,"correct":21},"D","初步评审有不符合评审标准的，在进行详细评审后再处理",{"key":26,"text":27,"correct":14},"E","招标文件没有说明的评标标准和方法不得作为评标依据","ABE","2020版教材P54-57 本题考查的是评标方法。选项C，招标人和审查委员会不接受申请人主动提出的澄清或说明。选项D，评标委员会依据上述标准对投标文件进行初步评审，有一项不符合评审标准的，应否决其投标。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]