[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102051":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102051,779,2,"多选题","招标方式中，邀请招标与公开招标比较，其缺点主要有（）等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","选择面窄，排斥了某些有竞争实力的潜在投标人",true,{"key":16,"text":17,"correct":14},"B","竞争的激烈程度相对较差",{"key":19,"text":20,"correct":21},"C","招标时间长",false,{"key":23,"text":24,"correct":21},"D","招标费用高",{"key":26,"text":27,"correct":21},"E","评标工作量较大","AB","2020版教材P39 本题考查的是招标方式。邀请招标选择范围较小，投标竞争的激烈程度相对较差，可能排斥了有竞争实力的投标人。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]