[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102043":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102043,779,2,"多选题","根据《标准设计施工总承包招标文件》的规定，下列关于工程总承包招标的说法，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程总承包招标程序与施工招标程序基本相同",true,{"key":16,"text":17,"correct":18},"B","工程总承包招标文件包括图纸和工程量清单",false,{"key":20,"text":21,"correct":14},"C","工程总承包招标编制的价格清单包括有关勘察设计费等内容",{"key":23,"text":24,"correct":18},"D","工程总承包招标的评标办法仅包括综合评价法",{"key":26,"text":27,"correct":14},"E","施工招标的评标办法包括综合评价法和经评审的最低投标价法","ACE","选项B错误，工程总承包招标文件不包括图纸和工程量清单。 选项D错误，标准设计施工总承包招标文件和标准施工招标文件的评标办法都包括综合评价法和经评审的最低投标价法。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]