[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102027":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102027,779,2,"多选题","采用最低评标价法对施工项目投标文件进行初步评审时的内容包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","形式评审",true,{"key":16,"text":17,"correct":14},"B","资格评审",{"key":19,"text":20,"correct":14},"C","响应性评审",{"key":22,"text":23,"correct":14},"D","施工组织设计",{"key":25,"text":26,"correct":27},"E","付款条件",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]