[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1102005,779,2,"多选题","资格预审阶段，资格审查委员会对施工项目投标人的资格审查分初步审查和详细审查两个阶段，属于详细审查的内容有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","企业资质条件",true,{"key":16,"text":17,"correct":14},"B","项目经理资格",{"key":19,"text":20,"correct":14},"C","企业信誉",{"key":22,"text":23,"correct":24},"D","施工组织方案",false,{"key":26,"text":27,"correct":24},"E","质量管理体系","ABC","本题考查的是资格预审程序。选项DE是评标阶段审查的内容。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]