[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101990":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101990,779,2,"多选题","招标人根据标准施工招标文件编制招标文件的做法正确的是（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","应不加修改地引用《标准施工招标文件》中的“评标办法前附表”",false,{"key":16,"text":17,"correct":14},"B","应根据项目的具体特点和实际需要引用《标准施工招标文件》中的“投标人须知”",{"key":19,"text":20,"correct":14},"C","“评标办法前附表”无需考虑招标项目的具体特点和实际需要",{"key":22,"text":23,"correct":24},"D","“投标人须知前附表”需要考虑招标项目的具体特点和实际需要",true,{"key":26,"text":27,"correct":24},"E","应不加修改地引用《标准施工招标文件》中的“通用合同条款”","DE","（1）招标人应根据标准施工招标文件，结合招标项目具体特点和实际需要，编制招标文件。",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]