[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101986,779,2,"多选题","公开招标过程中，发出招标公告后至开标前的主要工作内容包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","办理招标备案",false,{"key":16,"text":17,"correct":18},"B","资格预审",true,{"key":20,"text":21,"correct":18},"C","发售招标文件",{"key":23,"text":24,"correct":18},"D","解答投标人的质疑",{"key":26,"text":27,"correct":18},"E","组织现场考察","BCDE","",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]