[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101965":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101965,779,2,"多选题","下列建设工程进度控制任务中，属于设计准备阶段进度控制任务的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制工程项目总进度计划",true,{"key":16,"text":17,"correct":18},"B","编制详细的出图计划",false,{"key":20,"text":21,"correct":14},"C","进行工期目标和进度控制决策",{"key":23,"text":24,"correct":14},"D","进行环境及施工现场条件的调查和分析",{"key":26,"text":27,"correct":18},"E","编制工程年、季、月实施计划","ACD","建设工程实施阶段进度控制的主要任务",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]