[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1101964":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1101964,779,2,"多选题","下列建设工程进度影响因素中，属于组织管理因素的有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","业主使用要求改变而变更设计",false,{"key":16,"text":17,"correct":18},"B","向有关部门提出各种审批手续的延误",true,{"key":20,"text":21,"correct":18},"C","计划安排不周密导致停工待料",{"key":23,"text":24,"correct":14},"D","施工图纸供应不及时和不配套",{"key":26,"text":27,"correct":14},"E","有关方拖欠资金","BC","（1）业主因素。如业主使用要求改变而进行设计变更等。 （2）勘察设计因素。施工图纸供应不及时、不配套等。 （3）施工技术因素。（4）自然环境因素。 （5）社会环境因素。 （6）组织管理因素。如向有关部门提出各种申请审批手续的延误；计划安排不周密，组织协调不力等",{"id":6,"name":31,"category":32,"favorite":33},"合同管理","建筑工程",0]